· Engr. Mateen Ul Hassan · Project Controls · 2 min read

Case Study: 1,073-Activity Master Schedule for the Baltimore Container Terminal

An in-depth breakdown of the integrated master schedule, seasonal dredging windows, and cost/resource loading for the SPCT container terminal development in Baltimore, Maryland.

Large commercial shipping port and container cranes

The South Port Container Terminal (SPCT) development in Baltimore, Maryland represented a complex multi-year infrastructure program with an indicative budget of ,000,000 USD spanning 33 months of design and execution.

As Planning & Scheduling Engineer, Engr. Mateen Ul Hassan built the complete integrated master schedule hierarchy consisting of 1,073 activities in Oracle Primavera P6 Professional (Project ID: SPCT-M-1).

Program Architecture & WBS Structure

The schedule was architected into a strict master-to-detail hierarchy that preserved visibility from executive milestones down to weekly site work:

  • SPCT-M-1.1 Key Contract Milestones: 29 major commercial and contractual deadlines.
  • SPCT-M-1.2 Key Project Milestones: 11 executive progress gates.
  • SPCT-M-1.3 Design Phase: 109 activities tracking 60%, 90%, and Issued for Construction (IFC) review packages for dredging, Dredged Material Containment Facility (DMCF), wharf, and landside works.
  • Construction & Marine Execution: 924 activities covering mobilization, seasonal dredging windows, wharf piling and deck construction, container yard pavements, gates, utilities, and testing.

Seasonal Dredging Windows & Critical Path Logic

Marine environmental regulations imposed strict seasonal dredging windows restricted to 1 October through 31 March. Dredging mobilization and production cycles were modeled as driving milestones linked to environmental compliance dates. This seasonal window shaped the entire marine sequence:

  1. Substantial completion milestones were decoupled for wharf construction, landside container yards, the DMCF, and main channel dredging.
  2. Floating plant mobilization was scheduled to avoid demurrage penalties while meeting dredging volume targets.

Cost & Resource Loading

The entire budget was loaded across 7 dedicated cost accounts:

CodeCost AccountBudget (USD)Loading Method
01Design Phase (Dredging, DMCF, Wharf, Landside),150,000Resource-driven
02Mobilisation & Preliminaries,700,000Resource + Lump sum
03Dredging Works,650,000Resource-driven
04DMCF Facility,400,000Resource + Lump sum
05Wharf Construction,950,000Resource + Lump sum
06Landside Yard, Gate & Utilities,900,000Resource + Lump sum
07Testing, Commissioning & Close-out,250,000Resource-driven
TotalBudget at Completion (BAC),000,000100% Loaded

Peak monthly spend reached ,894,556 in October 2027 with peak site and marine manpower of 222 personnel. Through rigorous baseline locking and monthly Earned Value Management (SPI/CPI analysis), the project maintained schedule float and clear variance forecasts.